Cpk calculation compares how far your process average is from the nearest specification limit with the natural spread of the process. Cpk is the smaller of (USL − mean) ÷ 3σ and (mean − LSL) ÷ 3σ. Cp ignores centring and shows potential capability. Many automotive customers expect a Cpk of at least 1.33 for key characteristics.
What is SPC?
SPC, or statistical process control, is a way of measuring a process over time to tell normal variation apart from signals that something has changed. It lets you act on real problems early, and leave a stable process alone.
Every process varies a little. That everyday variation from many small influences is called common cause variation. A sudden shift from a worn tool, a new material batch or a changed setting is called special cause variation. SPC is about spotting the second without overreacting to the first.
What is a control chart?
A control chart is a graph of a measurement over time with a centre line for the average and two control limits calculated from the process itself. Points inside the limits with no unusual pattern suggest a stable process. The ASQ guide to control charts covers the main chart types.
The common types are:
- X-bar and R chart: for measurements taken in small groups, such as 5 parts every hour. One chart tracks the average, the other the range.
- Individuals (I-MR) chart: for one measurement at a time, such as one reading per batch.
- p-chart: for the proportion of defective parts, when you record pass or fail rather than a measurement.
The most common confusion is between control limits and specification limits:
Control limits | Specification limits | |
|---|---|---|
Where they come from | Calculated from your process data | Set by the customer or drawing |
What they tell you | Whether the process is stable | Whether a part is acceptable |
Typical width | About 3 standard deviations either side of the average | The tolerance on the drawing |
How do you read a control chart?
Read a control chart by looking for signals that the process has changed, not just points outside the limits. Commonly used rules flag:
- A point outside a control limit
- A run of around seven or eight points in a row on one side of the centre line
- A steady trend of six or more points rising or falling
- Points repeatedly close to one control limit
When a signal appears, stop and investigate what changed: tool, material, setting, operator or measurement. Our guide on how AI helps find the root cause of recurring quality problems covers that next step.
What are Cp and Cpk?
Cp and Cpk are process capability indices: they compare the width of your specification with the natural spread of your process. Cp shows what the process could achieve if perfectly centred. Cpk shows what it actually achieves, taking the position of the average into account. ASQ's page on process capability gives more background.
C_p = \frac{USL - LSL}{6\sigma}
C_{pk} = \min\left(\frac{USL - \bar{x}}{3\sigma},\; \frac{\bar{x} - LSL}{3\sigma}\right)
Here USL is the upper specification limit, LSL is the lower specification limit, x̄ is the process average and σ (sigma) is the standard deviation, which measures how spread out the readings are.
How do you calculate Cp and Cpk step by step?
To calculate Cp and Cpk, find the specification limits, calculate the average and standard deviation of your measurements, then apply the two formulas. Here is a worked example.
Example: A shaft diameter is specified as 20.00 ± 0.05 mm, so the USL is 20.05 mm and the LSL is 19.95 mm. From 25 measured parts on a stable process, the average is 20.01 mm and the standard deviation is 0.010 mm.
Step | Calculation | Result |
|---|---|---|
Cp | (20.05 − 19.95) ÷ (6 × 0.010) = 0.10 ÷ 0.06 | 1.67 |
Upper side | (20.05 − 20.01) ÷ (3 × 0.010) = 0.04 ÷ 0.03 | 1.33 |
Lower side | (20.01 − 19.95) ÷ (3 × 0.010) = 0.06 ÷ 0.03 | 2.00 |
Cpk | The smaller of 1.33 and 2.00 | 1.33 |
The process has a Cp of 1.67 but a Cpk of 1.33, because the average sits 0.01 mm above the target. Re-centring the process at 20.00 mm would raise Cpk to 1.67 without reducing variation at all.
In Excel, use =AVERAGE(range) for the average and =STDEV.S(range) for the standard deviation. Strictly, using the overall standard deviation of all readings gives Ppk rather than Cpk (explained below), but for a stable process the two are usually close.
What is a good Cpk value?
A Cpk of 1.33 is a common minimum for important characteristics, and many automotive customers ask for 1.67 on new parts or critical characteristics. Below 1.00, the process is producing, or is close to producing, parts outside specification.
Cpk | What it means | Distance from average to nearest limit |
|---|---|---|
Below 1.00 | Not capable: some parts will be out of specification | Less than 3σ |
1.00 to 1.33 | Marginal: needs close watching and improvement | 3σ to 4σ |
1.33 | A common minimum requirement | 4σ |
1.67 | Often required for new parts and critical characteristics | 5σ |
2.00 | Very capable | 6σ |
Always check your customer's own requirements, such as their supplier quality manual or PPAP (production part approval process) requirements, because they decide what is acceptable for your parts.
What is the difference between Cpk and Ppk?
Cpk uses the short-term variation within small groups of parts, while Ppk uses the overall variation across all the data collected. Cpk shows what the process can do; Ppk shows what it actually delivered over the period, including drifts between groups.
Customers often ask for Ppk in initial studies for new parts and Cpk for ongoing production. If Ppk is much lower than Cpk, the process is drifting over time, and a control chart will usually show where.
What are the most common SPC and Cpk mistakes?
The most common mistakes give a Cpk number that looks precise but means little. Watch for these:
- Calculating Cpk before checking that the process is stable
- Treating control limits as specification limits, or the reverse
- Using too few readings, such as 5 or 10 parts
- Ignoring measurement error: check your gauge with a measurement system analysis (MSA) first
- Rounding readings so much that small variation disappears
- Assuming the data follows a normal bell curve when it clearly does not
Where does AI help with SPC?
AI helps with the repetitive parts of SPC: collecting readings, plotting charts, flagging signals and preparing evidence for customers and auditors.
- Collecting readings from inspection reports, spreadsheets or photos of filled-in check sheets
- Plotting control charts automatically for each part and characteristic
- Flagging signals and alerting the quality head as soon as a rule is broken
- Calculating Cp and Cpk every month for each key characteristic
- Preparing evidence for PPAP submissions, customer audits and IATF audits
Osvik's quality documentation and audit readiness solution keeps inspection and capability records organised and ready when a customer asks. For suppliers to vehicle makers, see how we work with auto component manufacturers. If your checks are visual rather than measured, read our guide to AI visual inspection.
Start with one characteristic
Pick one critical dimension on one high-volume part, record 25 or more readings over a week and plot them. Check stability, then calculate Cp and Cpk. That single exercise will teach your team more about SPC than any training slide.
If you want help keeping these records complete and audit ready, book a free call. If a task repeats in your factory, tell us about it.
Frequently asked questions
What is Cpk in simple words?
Cpk tells you how well a process fits within its specification limits, taking into account both the spread of the process and how well it is centred. A higher Cpk means fewer parts are likely to fall outside the limits. A Cpk of 1.33 or more is a common target.
How do you calculate Cpk?
Work out the process average and standard deviation. Calculate (USL − average) ÷ (3 × standard deviation) and (average − LSL) ÷ (3 × standard deviation). Cpk is the smaller of the two results. Check that the process is stable on a control chart before you calculate.
What is a good Cpk value?
A Cpk of 1.33 is a common minimum for important characteristics, meaning the nearest specification limit is 4 standard deviations from the average. Many automotive customers require 1.67 for new parts or critical characteristics. Below 1.00, some parts are likely to be out of specification.
What is the difference between Cp and Cpk?
Cp compares the specification width with the process spread and assumes the process is perfectly centred. Cpk also accounts for where the average sits, so it is always equal to or lower than Cp. A high Cp with a lower Cpk means the process should be re-centred.
What is the difference between control limits and specification limits?
Control limits are calculated from your own process data and show whether the process is stable. Specification limits are set by the customer or drawing and define whether a part is acceptable. A process can be in control and still produce parts outside specification.
Can Cpk be calculated in Excel?
Yes. Use AVERAGE for the process average and STDEV.S for the standard deviation, then apply the Cpk formula. Using the overall standard deviation strictly gives Ppk, but for a stable process it is usually close to Cpk. Plot the data first to check for instability.